Which of the following is included in the aspects of defective work?

Prepare for ExAC Section 4 Exam for architects in Canada. Test your knowledge with comprehensive questions, including hints and explanations. Achieve success in your architectural journey.

Defective work refers to construction work or materials that fail to meet the established standards or specifications, leading to subpar results or unsafe conditions. The option that best fits within defective work is damage through carelessness. This is because carelessness directly results in compromised quality and safety of the work performed. For example, if workers do not handle materials properly or do not follow proper construction protocols, the end product may not perform as intended and can lead to structural issues or premature failure.

Other options, while related to project management and quality control, do not directly pertain to the nature of work itself being defective. The use of immature products refers to materials that have not fully developed in terms of quality or performance but does not inherently mean the work done with those products is defective unless the product's deficiencies directly impact the installation. Excessive overtime by workers may affect productivity and could lead to mistakes, but it does not constitute defective work unless the quality of the work suffers as a result. Inadequate document submission generally pertains to administrative or procedural shortcomings rather than the actual quality of the construction work itself.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy