What is the maximum time allowed for the contractor to inform after discovering hidden conditions during the project?

Prepare for ExAC Section 4 Exam for architects in Canada. Test your knowledge with comprehensive questions, including hints and explanations. Achieve success in your architectural journey.

The maximum time allowed for the contractor to inform the owner or architect after discovering hidden conditions during the project is five working days. This time frame is critical as it ensures that the project can continue without significant delays, while also allowing for prompt assessment and response to any unforeseen issues. By requiring timely notification, the contract aims to maintain clear communication and accountability, enabling the parties involved to evaluate the impact of the hidden conditions on the project scope, budget, and timeline. Prompt notification allows for the necessary adjustments to be made, reducing the likelihood of disputes and facilitating effective project management.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy